Arkanova Energy Corporation Installs Injection Plant and Pipeline

After receiving an injection well permit from the EPA, Provident Energy of Montana, LLC, a wholly owned subsidiary of Arkanova Energy Corporation, installs an injection plant and pipeline to commence the re-activation of waterflood operations on the company’s Montana lease acreage, the Two Medicine Cut Bank Sand Unit (TMCBSU).

Arkanova Energy Corporation (OTCBB: AKVA) (“Arkanova Energy”) has installed a water injection plant at the field office of Provident Energy, for the purpose of exercising the water injection permit that Provident received for the injection well Tribal Max #1-2817.  The project has been designed and implemented by Waterman Energy Inc of Montana. 



The injection plant features a two charge pumps and a positive displacement pump capable of flowing 1500 barrels of water per day to injection wells at a pressure of 2750 psi.  Four outlets from the main pump give Provident Energy the capability of pumping water to more potential injection wells as the project progresses.  The skid also has room for an additional pump to allow for greater pump capacity if deemed necessary.



Provident Energy intends to install approximately 8500 feet of 3” Fiberglass injection pipeline from the injection plant to the first injection well, Tribal Max 1-2817. The purpose of the pipeline is to carry water to injection wells.  Provident holds a UIC injection permit for the well Tribal Max 1-2817 issued by EPA Region 8 in March 2014, which allows injection at 2630 psi wellhead pressure.  The pipeline will follow existing pipeline easements and consist of 3” fiberglass pipe rated for 2900 Psi. 


                                         
 
Please note that any opinion, estimates or forecasts made by the authors of these reports are theirs alone and do not represent opinions, forecasts or predictions of Arkanova or its management. Arkanova does not by its reference or distribution of the report imply its
endorsement of or concurrence with such information, conclusions or recommendations.

T
he information in these reports is historical in nature, has not been updated, and is current only to the date indicated in the particular report. This information may no longer be accurate and therefore you should not rely on the information contained in these press releases. To the extent permitted by law, Arkanova Energy Corporation and its employees, agents and consultants exclude all liability for any loss or damage arising from the use of, or reliance on, any such information, whether or not caused by any negligent act or omission.
                                                                                                                     

                                     

 

                                         

 

                                         

 

                                          
Website Builder